View

Contracts Awarded

Each month Transit publishes the contracts awarded for capital projects and maintenance work with estimated cost, name of successful contractor, price and range of prices submitted. Contract information is available back to July 2004.

Regional Office: Work Type:
Value: Contract Type:
Month:
       

Title Date
Awarded
    Estimated
Value ($)
Auckland
SH1 Te Hana Rail Overbridge Nthbd P/L - PA3387 Oct-2009    
Kamo Bypass - Retaining Wall & Underpass Peer Review - PN3382 Oct-2009    
Walking & Cycling Auckland PA3344 Oct-2009    
North Roads Concept Development PA3371 Oct-2009    
Western Ring Route: Project Mgmt Svs PA3385 Oct-2009    
Western Ring Route: Project Mgmt Svs PA3381 Oct-2009    
SH1 Whangarei Southern Projects Communications PN3384 Oct-2009    
Western Ring Route: Residential Dwelling Demolition PA3379 Oct-2009    
Western Ring Route : SH20 Waterview Connection : Structure Design PA3343 Oct-2009    
McKinney ROad / Wech Drive Int Improvements PA3362 Oct-2009    
Aditional Waitemata Harbour Crossing PA3349 Oct-2009    
SH16 Widening Air Quality Monitoring Te Atatu to Massey PA3374 Oct-2009    
SH1 Dome Sthbd Passing Lane Extn: Stage 2 Safety Audit PA3378 Oct-2009    
Peer Review and Revision of 'Draft NZTA Standard for Prouding .... PA3372 Oct-2009    
Peer Review & Revision of Draft NZTA Standard for Producing Air Quality PA337 Oct-2009    
SH11 Lily Pond Bridge to Quarry Seal Widening PN3370 Oct-2009    
Warkworth Pedestrian & Cycling Design Oct-2009    
Stage 3 Detailed Design Road Safety Audit-SH11 Lily Pond PN3370 Oct-2009    
Christchurch
Pound Road Intersection Upgrade Oct-2009    
1,667,289.00
SH 1 & 8 Guardrail Installations Oct-2009    
143,800.00
SH6 Ten Mile creek Bridge Relocation Oct-2009    
410,000.00
Crushington Guardrail Oct-2009    
145,000.00
SH73 Pegleg to Brake Check Area Wide Treatment 2009/2010 Oct-2009    
156,085.00
Region 12 West Coast Pavement Marking 200-2013 Oct-2009    
3,327,316.00
Dunedin
Central Otago Minor Safety Works 2009/10 Oct-2009    
470,000.00
Central Southland Rehabilitation 2009/10 Oct-2009    
1,341,583.00
Crawford Street Safety Improvements Oct-2009    
491,000.00
Eastern Southland Rehabilitation 2009/10 Oct-2009    
1,129,300.00
Central Otago State Highways Pavement Rehabilitation 2009/10 Oct-2009    
1,660,860.00
North Western Southland Rehabilitation 2009/10 Oct-2009    
516,676.00
Hamilton
State Highway 2 Tauranga Eastern Link Commissioning Services Oct-2009    
17,000.00
State Highway 2 Tauranga Eastern Link Commissioning Services Oct-2009    
15,000.00
State Highway 2 Tauranga Eastern Link Commissioning Services Oct-2009    
15,000.00
Central Waikato Resealing Oct-2009    
3,020,400.00
State Highway 2 Tauranga Eastern Link - Tangata Whenua Advisor Oct-2009    
7,200.00
Napier
Safety Improvements Gisborne 2009/2010 - 1032 Oct-2009    
634,780.00
Safety Improvements, Hawke's Bay, 2009/2010 - (1037) Oct-2009    
1,086,467.00
HB Expressway Southern Extension York Road to Maraekakaho Road (1036) Oct-2009    
7,960,248.00
Highway Pavement Recycling HB 2009/2010 (1045) Oct-2009    
3,369,357.00
Highway Recycling, Gisborne 2009/2010 (1046) Oct-2009    
4,559,992.00
Bridge Repainting Gisborne and Hawke's Bay 2009/2010 (1031) Oct-2009    
724,083.00
Wanganui
SH 3 Carlton Ave/Alma/Jackson Intersection - TRW 1716 Oct-2009    
1,695,069.00
SH 4 North of Taumarunui Area Wide Treatments 2009/10 - TRW 1715 Oct-2009    
1,098,000.00
SH 3 London Street Improvements - TRW 1717 Oct-2009    
750,000.00
Taranaki State Highway Resurfacing 2009/10 - TRT 1296 Oct-2009    
2,784,915.00
SH 1 Waiauti Stream Bridge Realignment - PSW 148 (MSQA) Oct-2009    
170,000.00
SH 3 London Street High School Access - PSW 165 (MSQA) Oct-2009    
50,000.00
SH 3 Scowns Hill Passing Lanes - TRT 1300 Oct-2009    
1,882,038.00
SH 3/4 Wikitoria Road Intersection Improvements - PSW 187 (MSQA) Oct-2009    
70,000.00
Wellington
Local Roads Minor Safety & Kerb and Channel 09/10 Oct-2009    
221,217.00
SH1 Dashwood Safety Improvements RP 43/3.168 Oct-2009    
266,650.00
Bridge Replacement Jenkins #2 and Roses Overflow Oct-2009